Horns Rev 1
Offshore Substation
 
Customer: Energinet DK (HSM Offshore BV)Location: The Danish part of the North SeaPeriod: 2001 - 2002Topside Weight: 4700 tonsCapacity: 1200 MW
Semco Maritime was awarded the contract for design and supply of low-voltage switchboards and monitoring system for the platform.
Competences and systems
- Low-voltage switchboards, PLC switchboards and UPS systems
 - Fire detection and firefighting systems
 - Line-of-sight communication system
 - Wind turbine VHF communication system
 - Weather station
 - CCTV system
 - Project management
 
Highlights
- The wind farm is situated in one of the harsher parts (water depth only 6 metres) of the North Sea with strong winds, extreme tidal flows and rapid currents
 - The largest offshore wind farm at that time
 - The project was performed on time
 - Positive feedback from customer